1. Introduction (duration: 15 min)
Speaker: A. Kors Environmental manager Programme Agency HWBP
Mr Kors will give a description of the high water protection programme which will include the following points:
- Reasons for the HWBP
- Scope of the programme
- Assignment and organisation of the programme agency

2. Plan study phase (duration: 30 min)
Speaker: A. v/d Laan, Technical Manager Programme Agency HWBP
Mr van der Laan will elaborate on the process surrounding the plan study phase. Among other things, he will explain the following topics:
- Granting subsidies
- Management and quality assurance of the projects
- Guidance documents
- Tests of the HWBP

3. Execution of HWBP projects (duration: 30 min)
Speaker: P. Meesen, Contract Manager Programme Agency HWBP
Among other things, Mr Meesen will explain problems that (can) occur during the realisation phase of projects. In addition, he will discuss the following topics:
- New contract forms
- Innovations
- Risks

4. Highlighting HWBP project(s) of WS Rivierenland (duration: 30 min)
Speaker: F. van den Berg, Project coordinator Waterschap Rivierenland
Mr van den Berg will elaborate on specific projects and practical experiences of Waterschap Rivierenland

Location

TU Delft, Fac. CiTG (room B)

Stevinweg 1, Delft

Organiser

Construction and Hydraulic Engineering

Programme Agency HWBP

Name and contact details for information

Inge van Rooij

i.vanrooij@tudelft.nl