The restoration of flood defences involves many hydraulic and geotechnical challenges, leading to innovative technical solutions that we will see in practice with this excursion. The dyke improvement KIS is in full swing and there we will see the following dyke improvement techniques:
Location Gelkens:
- installation of bored piles with concrete cover
- soil filling to improve the inward stability

Location Nieuw-Lekkerk
- installation of diaphragm walls

Location Sluis / Opperstok
- raising the height of the dike including temporary over height
- emptying ditches at the toe of the dike
- installing bored piles

Location Streefkerk
- raising the height of the dike including pore pressure measurements
- relocating cables and pipes

In preparation, you will receive a lecture by Bram de Fockert, project manager KIS on behalf of Waterschap Rivierenland, about the ins and outs of the KIS project.

Then Gerjan Westerhof, technical manager KIS on behalf of water board Rivierenland, will take us outside for an in-depth explanation.

To conclude the excursion, Henrike Branderhorst, department manager Water at Tauw, will give a presentation on the big task of the HWBP versus the new way of thinking; the water system of the future


13:00 - 13:30 Walk-in with coffee Project office Aannemers Combinatie Dijkverbetering Molenwaard former town hall Voorstraat 88 in Groot Ammers

13:30 - 13:40 Opening (Ernst Oosterveld | KIVI BW/ Tauw)

13:40 - 14:15 Welcome and presentation ins and outs dike reinforcement KIS (Bram de Fokkert | Project manager KIS/ WS Riviereland)

14:15 - 14:30 To the bus

14:30 - 16:00 Project visit by bus 12.7 km dike reinforcement led by: Gerjan Westerhof | Technical manager KIS/ WS Rivierenland

16:00 - 16:30 Presentation Water system of the future versus HWBP (Henrike Branderhorst | Tauw)

16:30 - 17:00 Closure and subsequent networking drinks project office contractors combination Molenwaard in Groot Ammers

17:00 End of official programme

PLEASE NOTE! Train passengers:
12:00 - 12:30 Gather at the bus in front of NS Station on Stationsweg, in Gorinchem
12:30 Departure to Project Office Contractors Combination Dike Improvement Molenwaard in Groot Ammers (former town hall Groot Ammers) approx. half an hour
17:00 - 17:30 Train passengers will be brought back to Station

**If possible, bring your own:
- safety jacket
- safety helmet
- safety shoes

Location

Project office KIS Contractors

Voorstraat 88, Groot Ammers

Organiser

Construction and Hydraulic Engineering

Name and contact details for information

Ernst Oosterveld Board member Department BW telf. 06 53 30 46 92

ernst.oosterveld@tauw.nl