Societal context
Rijkswaterstaat (RWS) manages the national highway and waterway networks, which include
approximately 127 ship locks and 157 movable bridges used daily by road and waterway traffic
across the Netherlands. Most of these assets were built in the 1950s and 1960s. Because of their
age, increasing traffic loads and harsh weather conditions, a significant number require major
renovation or replacement within approximately two decades. This work must be delivered
quickly and with minimal disruption to the public.
Innovation
Contractors currently design a unique solution for each asset, an engineer-to-order approach.
This leads to more engineering effort, longer project durations, a broad range of spare parts and
higher maintenance costs. RWS is therefore moving to a configure-to-order product platform in
which assets are configured from standardized building blocks. My project extended this
platform with quantitative reliability, availability and lifecycle cost (RAL) assessment. Today,
design variants are compared through subjective qualitative scoring. With the extended
platform, project teams can see quantitative metrics for each design choice and for the
complete asset during configuration selection, before a formal RAMS analysis. A key element of
the approach is the reuse of the existing standardized maintenance database at RWS (based on
NEN 2767) as the data source. This brings maintenance knowledge into the early design phase
through tooling and processes that RWS already uses.
Impact
The extended platform supports the RWS Asset Management 2.0 objective of balancing
performance, risk and cost throughout the asset lifecycle. Well-informed early design decisions
help ensure reliable assets with lower risk of unplanned downtime and lower lifecycle costs. The
prototype was demonstrated on the movement mechanism of the Schiphol Bridge, where user
acceptance testing with primary users and the platform maintainer confirmed that all project
objectives were met. The platform also provides a structured place to record operational data
and maintenance knowledge from existing assets, addressing the gap in knowledge transfer
from maintenance to design identified by stakeholders. Because the architecture is asset-type
independent, it can be extended to ship locks and other RWS assets, offering a reusable and
scalable foundation for faster and better-informed infrastructure decisions. For the public, this
means fewer unplanned closures of bridges and locks, less traffic disruption, and more effective
use of public funds.
Leadership and collaboration
Entering a largely new domain, I learned reliability engineering and studied the working
processes of several RWS departments in detail. Through structured interviews with asset
managers, technical managers, systems engineers, maintenance engineers and RAMS advisors,
I identified 57 problems across the asset lifecycle and combined these perspectives into one
coherent solution. I applied a structured systems engineering approach (V-model, ISO 15288,
SYSMOD) and sound software architecture practices, ensuring traceability from stakeholder
needs to the validated prototype. I worked closely with the platform’s external developer to
integrate the new components and wrote a user manual for users and the maintainer to support
continued use. In the foreword to my thesis, my RWS supervisors highlighted my “ability to