Presentations
Prevention is better: the design of watertight grout layers
In his lecture, Van Tol discussed the design of a watertight grout layer. It became clear that a guaranteed watertight design is not possible in practice, or is unaffordable. A certain optimum between permissible risk and cost will always have to be chosen. This was investigated by TU Delft by applying a failure probability model for a grout layer, analysing issues such as misalignment of the injection lance and location determination as possible sources of error.
In practice, the hydraulic resistance of a layer is always smaller than the resistance you would theoretically expect based on the material properties. Small defects have a big impact on the 'over all' resistance of the system. Conclusion: if you achieve 50% of the design resistance, then you have delivered a good product. However, it is then difficult to determine whether or not that 50% will lead to a calamity. If the flow comes evenly through the grout layer, then the risk is zero. If it comes through a single hole, then there is no problem as long as there remains enough cover and the hole remains filled with soil material. Only when excavation is carried out to just above the leak is a calamity, as the sand is forced out of the hole and then the flow rate (with material transport) increases explosively. Van Tol advocates installing 'dormant drainage' to deal with such calamities.
Questions from the audience mainly concerned these restrictive measures, such as applying dormant drainage. These dewaterings should be short in duration, to prevent damage to the surrounding area, but allow the builder to carry out remedial measures. In general, the competent authority will cooperate.
Leak management at the Griftpark in Utrecht
Leurink does not like to talk about Leak Management, because it sounds so negative. But practically speaking, the cement-bentonite wall built around Griftpark in the 1990s is indeed leaky.
But: in environmental circles, only zero emissions are permissible, and they are met. So, how so: leaky? Also, everything was realised within budget, so: the Griftpark is a success, even with leakage.
Leurink outlines the history of the site, the (polluting) activities that have taken place there and the geological soil structure, which shows that the Kedichem clay, to which the cement-bentonite wall connects, is not present throughout the site. A prognosis (with uncertainty limits) was prepared in advance for the flow to be extracted and treated. This distinguished between vertical (through the Kedichem layer) and horizontal (through the wall) inflowing water, with the contractor to be charged for the latter component. In practice, this did not happen because the overall system performed within the predetermined uncertainty interval. As a result, some more water was pumped and purified than calculated beforehand, but it fell within the uncertainty margins and did not result in adjustments to the abstraction system, purification or pipeline capacity.
The discussion revealed that the requirements set in the tendering procedure may have led to an overly expensive design.
Implementation aspects
According to Admiraal, the starting point must be that leaks cannot always be prevented, but that the risks must be managed.
First of all, steel sheet pile walls are discussed: causes of leaks can include obstacles, 'heavy' foundations that require heavy vibratory hammers and sometimes the need for reinforcement. The contractor can be prepared for these aspects through soil investigation and historical research, and Admiraal also mentions a number of things the contractor can do to reduce the risk of leakage in practice. These range from working carefully, via lock indicators and pre-drilling or fluidising to applying all kinds of fillers to make the locks less permeable.
Admiraal then similarly discusses a number of other techniques to apply water-reducing walls, such as grout piles and diaphragm walls.
After vertical walls, horizontal layers such as:
- natural inhibitory layers
- underwater concrete
- artificial jet grout layer
- foil structures
Admiral's conclusions are:
Leaks occur easily but are difficult to control, therefore one must be aware of the risks and determine beforehand whether leaks are acceptable. In extreme cases, alternative construction methods that pose less risk should be adopted. He urges open communication between all parties involved.
Discussion: again, following this lecture, the need to weigh up the risks of possible leakage at an early stage and have precautionary measures in reserve is again raised. Nevertheless, it remains a difficult balancing act. The consequence is that investments (e.g. dormant drainage) are made that ultimately do not have to serve.
Leak detection: locating the problem
In his lecture, Slob discusses geoelectric techniques. These techniques are the most appropriate when it comes to leak detection, especially as they are reasonably fast. In particular, he elaborates on the ECR/EFT method recently introduced on the Dutch market by Texplor. In a way that is clear to everyone, Slob shows how the techniques in question work and what the possibilities and limitations are as a result. It is especially fascinating to learn that things like dimensions of leaks and depths can potentially be determined with this method. This does require additional effort. He also introduced listeners to a simpler version, in which measurements are taken while walking through the field, as it were, instead of the fixed set-up, which is rather labour-intensive.
The responses show that the methods in question do not have widespread familiarity, even less is known about how the method works. There is a rather subjective approach regarding the confidence placed in the method.
Leak repair
Firstly, the question is raised as to whether there should always be recovery. This was also raised in earlier lectures. The answer is "No", only when there are risks. While one such risk is water encumbrance, Lambert advocates not being too rigid about it. Water heaviness should be an aspect in the consideration, not a sacred number. Two other risks are settlement and hence damage, a slow process; and piping and hence soil transport, a disastrous and rapid process that should certainly not be solved by extra lowering of the water level. This only accelerates the process.
Options to prevent settlement damage include return pumping, when predetermined groundwater levels in the surrounding area are undercut. Sometimes this is a relatively simple and inexpensive measure.
In addition to traditional repair methods, which (when applied at some depth) are without exception expensive and labour-intensive, and also require accessibility to the exact leak site, there is a need for quick, simple repair methods that, while not leading to complete closure, reduce the water load to acceptable proportions.
Lambert describes a method under development: 'Biosealing', using the properties of subsoil, groundwater and leak. Feeding the micro-organisms naturally present in the soil causes them to multiply rapidly, leading to clogging. Formation of iron sulphide makes the blockage more durable. These mechanisms have been tested in the laboratory; a field experiment is currently underway.
The discussion looks at the durability (FeS formation) and the explanation of the mechanism. There is also a cautionary note: to what extent is it to be feared that tarnishing of the (steel) sheet piling will occur.
Forum discussion
What is lesson learned this afternoon?
What has not been discussed? What is it about?
Michael Loxham, GeoDelft
Points out the conceptual strength of biomanipulation. In Brussels today, the key word is 'sustainability', both of structures and of environmental solutions.
Translating that to our profession means pursuing solutions on a local scale and for the long term. To achieve sustainability, we need to work soil, but through small changes. Not in the crude way.
Bacteria should be seen as our little collaborators who do that for us, which is why bacteria are useful. Then we can respond to sustainability requirements and exploit opportunities.
Karel Brons, Nederhorst
Revisits the need to prevent leaks as much as possible, but on the other hand learn to live with the knowledge that leaks will occur. Therefore, respond to them at an early stage. He cites reliance on grout columns as an example. If leakage is not permissible, this reliance should not be too great. We do not yet know much about the dimensions of columns as they are formed in the ground, and we know from (some) observations that the results are sometimes disappointing.
Barto Admiraal, VWSG
Mentions the advantage of columns that you can work in all soil types, but in risk analysis you have to look at limitations. In risk areas, you should do tests beforehand.
He also notes that different provinces have different requirements regarding permissible water nuisance and deal with them differently. Therefore, the consultant indicates water objections that are on the high side to get permission. The well bailer sizes up to the high water load and nevertheless fails to get the well dry. If no comprehensive on-site investigation is carried out (pumping test), you have to live with these uncertainties. The client is not waiting for a report stating that the water load could also be 10 times higher or 10 times lower. Yet these are 'normal' uncertainties.
Discussion regarding Biosealing
BioSealing is a new technique. It does not replace all previous techniques, but should be seen as an attractive and low-cost additional option. Could possibly also be used to address local seepage problems.
Finally, it is noted that car park owners suffer more from leaky roofs than leaky floors. This is a good signal to get on the drink.

